Sylmar Ground Return System Replacement Project (SGRS Project)

7 Documents in Project

Summary

SCH Number
2010091044
Lead Agency
City of Los Angeles
Document Title
Sylmar Ground Return System Replacement Project (SGRS Project)
Document Type
NOD - Notice of Determination
Received
Posted
8/5/2016
Document Description
The Los Angeles Dept. of Water and Power is proposing to replace the existing marine electrode portions of the SGRS. The replacement facility will be located in the vicinity of the existing SGRS marine facility in Santa Monica Bay. While the new marine facility would be in a different alignment than the existing, it would serve the same purpose and function as the existing facility. The SGRS is an integral component of the Pacific Direct Current Intertie Transmission Line (PDCI), which transmits bulk power between Los Angeles and the Pacific Northwest. The PDCI is a direct current system, and it cannot operate reliably without a ground return system. Due to physical and operational system deficiencies with the existing marine facility of the SGRS, its replacement is proposed to increase the reliability and stability of the power generation and delivery system for the Southern CA; to continue to meet current and projected demand for power in the region; and to help increase the available share of renewable resource energy for the PDCI partners.

Contact Information

Name
Nancy Chung
Agency Name
City of Los Angeles Department of Water and Power
Contact Types
Lead/Public Agency

Location

Cities
Los Angeles, Los Angeles, City of
Counties
Los Angeles
Cross Streets
Pacific Coast Hwy and Sunset Blvd.
State Highways
Pacific Coast Hwy
Schools
Multiple
Waterways
Santa Monica Bay
Other Location Info
Pacific Palisades

Notice of Determination

Approving Agency
City of Los Angeles Board of Water and Power Commissioners
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print