San Diego Marriott & Marina Facilities Improvement and Port Master Plan Amendment Project
6 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2010091012
- Lead Agency
- San Diego, Port of
- Document Title
- San Diego Marriott & Marina Facilities Improvement and Port Master Plan Amendment Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 12/14/2011
- Present Land Use
- Commercial Recreation, Promenade.
- Document Description
- The project is upgrades to the San Diego Marriott Marquis & Marina to modernize the hotel facility. Includes: 1) demolition of the existing Marriott Hall ballroom, landscape, marina restroom bldg and asphalt, and removal of 403 surface and covered parking spaces; 2) construction of a new and expanded Marriott Hall with ballroom and exhibit space, an outdoor event area (Marina Terrace), public access corridor improvements between the Marriott and adjacent Hyatt Hotel (Marina Walk), replacement of marina restroom bldg and landscaping; 3) relocation of 2 existing mechanical cooling towers and addition of 2 new cooling towers. Construction is estimated to be complete in 20 months. The project includes a Port Master Plan Amendment (PMPA).
- Contact Information
-
Wileen Manaois
San Diego, Port of
3165 Pacific Highway
San Diego, CA 92101
Phone : (619) 686-6282
wmanaois@portofsandiego.org
Location
- Coordinates
- 32°42'30"N 117°09'54"W
- Cities
- San Diego
- Counties
- San Diego
- Cross Streets
- West Harbor Dr. & Front St., 1st Avenue
- Zip
- 92101
- Total Acres
- 5.4
- Parcel #
- 760-016-05-00
- State Highways
- I-5
- Railways
- BNSF
- Airports
- SDIA
- Schools
- Perkins Elem, Garfield High, San Diego High
- Waterways
- San Diego Bay
Notice of Determination
- Approving Agency
- San Diego Unified Port District
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- SDUPD Clerk's Office, 3165 Pacific Hwy, San Diego, CA 92101.
Determinations
- (1) The project will have a significant impact on the environment
- Yes
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- No
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.