Approval of the Installation Restoration Site 15(IR15) Feasibility Study/Remedial Action Plan, within Investigation Area C1, Lennar Mare Island, Vallejo,CA

2 Documents in Project

Summary

SCH Number
2010082083
Lead Agency
Department of Toxic Substances Control
Document Title
Approval of the Installation Restoration Site 15(IR15) Feasibility Study/Remedial Action Plan, within Investigation Area C1, Lennar Mare Island, Vallejo,CA
Document Type
NOD - Notice of Determination
Received
Posted
11/17/2010
Present Land Use
Commercial/Industrial
Document Description
Preparation and approval of the Revised Draft for Public Review IR15 Feasibility Study/Remedial Action Plan, Investigation Area C1, Lennar mare Island, Vallejo, California (FS/Rap) by the State of California Environmental Protection Agency, Department of Toxic Substances Control (DTSC). The FS/RAP proposes remediation of soil and groundwater contamination at Installation Restoration Site 15 (IR 15). This area is part of a larger parcel (called the Easter Early Transfer Parcel) that was transferred from the Unite State Department of Navy to Lennar Mare Island, LLC (LMI). The FS/RAP in incorporated by reference.

Contact Information

Name
Janet Naito
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Cities
Vallejo
Counties
Solano
Cross Streets
Waterfront Ave, Kansas Street, Arizona Street
Zip
94592
Total Acres
3.5
Parcel #
066-050-090
State Highways
Hwy 37
Railways
SF Bay RR- Mare Island
Schools
Mare Island Elementary
Waterways
Mare Island Strait, Carquinez Strait

Notice of Determination

Approving Agency
Department of Toxic Subsance Control
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.