WRSP Fiddyment Ranch, Phase 3 Specific Plan Amendment

6 Documents in Project

Summary

SCH Number
2010082075
Lead Agency
Plumas County
Document Title
WRSP Fiddyment Ranch, Phase 3 Specific Plan Amendment
Document Type
NOD - Notice of Determination
Received
Posted
4/24/2014
Document Description
The applicant requests approval of a General Plan Amendment, Specific Plan Amendment, Rezone, Development Agreement Amendment and Certification of a Final Subsequent Environmental Impact Report to amend West Roseville Specific Plan (WRSP) to accommodate 1,661 additional residential units (580 Low Density Residential units, 609 Medium Density Residential Units, and 472 High Density Residential Units) in Fiddyment Ranch Phase 2 and 3. The revised land use plan will not change the footprint of the WRSP, but would redistribute certain land uses with the project area. The project proposes to change development densities within certain Fiddyment Ranch residential parcels. Additionally, the project proposes to create a new large lot tentative map for the project area and subdivide three of the new large lot parcels into 414 residential lots.

Contact Information

Name
Ron Miller
Agency Name
City of Roseville
Contact Types
Lead/Public Agency

Location

Cities
Roseville
Counties
Placer
Cross Streets
County Road A-15 and State Highway 89
Zip
95971
Total Acres
89.17
Parcel #
133-080-031, -032, -036 and -037
State Highways
Hwy 89
Railways
UPRR
Waterways
Sulphur Creek, Middle Fork Feather River, Calf Paster, etc.
Township
22N
Range
13E
Section
29,30
Base
MBD&M

Notice of Determination

Approving Agency
Roseville City Council
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.