Palermo-East Nicolaus 115-kV Transmission Line Reconstruction Project

10 Documents in Project

Summary

SCH Number
2010082014
Lead Agency
Public Utilities Commission (California Public Utilities Commission)
Document Title
Palermo-East Nicolaus 115-kV Transmission Line Reconstruction Project
Document Type
NOD - Notice of Determination
Received

Document Description
The project would include the reconductoring of both spans of the double circuit transmission line with approximately 45 miles of new conductor. To accommodate reconductoring, replacement of the existing lattice steel towers would be required. Towers would be replaces with a combination of hybrid tubular steel poles, and lattice poles, Construction time: 12-18 months.

Contact Information
Iain Fisher
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CA 94102-3298

(415) 355-5580

Location

Coordinates
39°9'54"N 121°33'35.5"W
Cities
Yuba City Oroville Marysville
Counties
Yuba Sutter Butte
Cross Streets
several
Zip
95901
Total Acres
45 miles-a route
State Highways
SR 20,65,70
Railways
SPRR, UPRR
Airports
Yuba County, Siller Bros Inc. -
Schools
several
Waterways
several
Other Location Info
City: Nicolaus
Other Information
Airports cont. Aviation (a private airstrip)

Notice of Determination

Approving Agency
California Public Utilities Commission
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
California Public Utilities Commission 505 Van Ness Avenue Rm 4A San Francisco, CA 94102-3298

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No
Download CSV New Search