Palermo-East Nicolaus 115-kV Transmission Line Reconstruction Project
10 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2010082014
- Lead Agency
- Public Utilities Commission, California (California Public Utilities Commission)
- Document Title
- Palermo-East Nicolaus 115-kV Transmission Line Reconstruction Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 11/22/2010
- Present Land Use
- Various
- Document Description
- The project would include the reconductoring of both spans of the double circuit transmission line with approximately 45 miles of new conductor. To accommodate reconductoring, replacement of the existing lattice steel towers would be required. Towers would be replaces with a combination of hybrid tubular steel poles, and lattice poles, Construction time: 12-18 months.
- Contact Information
-
Iain Fisher
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CA 94102-3298
Phone : (415) 355-5580
Location
- Coordinates
- 39°9'54"N 121°33'35.5"W
- Cities
- Marysville Oroville Yuba City
- Counties
- Butte Sutter Yuba
- Cross Streets
- several
- Zip
- 95901
- Total Acres
- 45 miles-a route
- State Highways
- SR 20,65,70
- Railways
- SPRR, UPRR
- Airports
- Yuba County, Siller Bros Inc. -
- Schools
- several
- Waterways
- several
- Other Location Info
- City: Nicolaus
- Other Information
- Airports cont. Aviation (a private airstrip)
Notice of Determination
- Approving Agency
- California Public Utilities Commission
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- California Public Utilities Commission 505 Van Ness Avenue Rm 4A San Francisco, CA 94102-3298
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.