Palermo-East Nicolaus 115-kV Transmission Line Reconstruction Project
10 Documents in Project
Summary
SCH Number
2010082014
Lead Agency
California Public Utilities Commission
(CPUC)
Document Title
Palermo-East Nicolaus 115-kV Transmission Line Reconstruction Project
Document Type
MND - Mitigated Negative Declaration
Received
Present Land Use
Various
Document Description
The project would include the reconductoring of both spans of the double-circuit transmission line with approximately 45 miles of new conductor. To accommodate reconductoring, replacement of the existing lattice steel towers would be required. The existing Milliken towers, originally constructed in the early 1900s, would not support the new conductor because of higher tension loads. The towers would be replaced with a combination of hybrid tubular steel poles, tubular steel poles, and lattice steel poles. Constrution would take 12 to 18 months.
Contact Information
Name
Iain Fisher
Agency Name
California Public Utilities Commission
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Marysville, Oroville, Yuba City
Counties
Butte, Sutter, Yuba
Zip
95901
Total Acres
45 miles-a route
State Highways
SR 20,65,70
Railways
SPRR, UPRR
Airports
Yuba County, Siller Bros Inc. -
Other Location Info
City: Nicolaus
Other Information
Airports cont. Aviation (a private airstrip)
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
California Department of Conservation (DOC), California Department of Fish and Wildlife, North Central Region 2 (CDFW), California Department of Parks and Recreation, California Department of Transportation, District 3 (DOT), California Highway Patrol, California Native American Heritage Commission (NAHC), California Regional Water Quality Control Board, Central Valley Redding Region 5 (RWQCB), California Regional Water Quality Control Board, Central Valley Sacramento Region 5 (RWQCB), California State Lands Commission (SLC), Caltrans, Division of Aeronautics, Department of Water Resources, Resources Agency
Development Types
Other (115-kV Transmission Line Reconductoring)
Local Actions
Other
Project Issues
Aesthetics, Agriculture and Forestry Resources, Air Quality, Biological Resources, Cultural Resources, Cumulative Effects, Drainage/Absorption, Economics/Jobs, Flood Plain/Flooding, Geology/Soils, Growth Inducement, Hazards & Hazardous Materials, Hydrology/Water Quality, Land Use/Planning, Mineral Resources, Noise, Population/Housing, Public Services, Recreation, Schools/Universities, Septic System, Sewer Capacity, Solid Waste, Transportation, Vegetation, Wetland/Riparian, Wildfire
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.