BV8 State Water Project Turnout (California Endangered Species Act (CESA) Incidental Take Permit No. 2081-2011-056-04

8 Documents in Project

Summary

SCH Number
2010081076
Lead Agency
Buena Vista Water Storage District
Document Title
BV8 State Water Project Turnout (California Endangered Species Act (CESA) Incidental Take Permit No. 2081-2011-056-04
Document Type
NOD - Notice of Determination
Received
Posted
6/13/2012
Document Description
The Notice of Determination is for the Amended ITP No. 2081-2011-056-04 Amendment No. 1. The amended ITP adds giant kangaroo rat (Dipodomys ingens) to the Covered Species list. The proposed Project includes the construction of a new water turnout on the Department of Water Resources' (DWR) California Aqueduct to deliver water into Buena Vista Water Storage District's (BVWSD) West Side Canal via a new underground pipeline and outlet structure. The turnout will be constructed on the east bank of the Aqueduct consisting of a 78 inch by 78 inch sluice gate and appurtenances. Within the DWR's right-of-way there will also be a meter vault, instrument building and appurtenances. An underground pipeline will connect the turnout structure to the outlet structure on the West Side Canal. The pipeline will be approximately 1,510 feet long and 78-inch diameter reinforced concrete pipe. The trench required for pipe installation will be approximately 30 feet wide by 13 feet deep with a temporary construction easement of 100 feet wide along the length of the pipeline. The pipeline will run underground across the Kern River Flood Channel.

Contact Information

Name
Brandon Sanderson
Agency Name
Department of Fish and Game (DFG)
Contact Types
Lead/Public Agency

Location

Counties
Kern
Zip
93206
Parcel #
159-140-09, 159-130-03
State Highways
No
Railways
No
Airports
No
Schools
No
Waterways
California Aqueduct, Kern River Flood Channel, West Side Canal, Short Main Canal, Arizona Canal,
Township
30S
Range
24E
Section
9
Base
MDB&M
Other Location Info
City/Nearest Community: Buttonwillow
Other Information
Waterways Continued: Florida Drain, Freeborn Ditch, Main Drain, Section 3-4 Drain.

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print