Recycled Water Ponds Expansion and Optimization Project
7 Documents in Project
Summary
SCH Number
2010081044
Lead Agency
Eastern Municipal Water District
(EMWD)
Document Title
Recycled Water Ponds Expansion and Optimization Project
Document Type
NOD - Notice of Determination
Received
Posted
12/22/2015
Present Land Use
Public/Semi-Public Facilities/Utilities
Document Description
Viewshed Permit and Use Permit to allow: 1) construction of a 42,840 gallons per year winery including a 6,779 sf winery building, 303 sf outdoor tasting area, 6,245 sf underground barrel storage cave, and 15 parking spaces (14 standard and one ADA space); 2) widening of the existing driveway to 20-ft and installation of a left turn lane on Silverado Trai; 3) No more than 10 employees; 4) installation of an in-ground wastewater treatment system, installation of three 12,000 gallon water tanks; 5) A visitation and marketing program of up to 14 daily visitors from November 1 to August 31, up to10 daily visitors from September 1 to October 31, and three events per year for up to 50 guests; and 6) onside consumption of wines produces onsite and purchased from the winery in the outdoor patio area and indoor wine tasting area (break room) (AB2004 Business and Professions Code Section 23358, 23390, & 23396.5).
The project consists of the construction of a new recycled water storage pond at the North Trumble Recycled Water Storage Pond site and improvements (optimization) at the Case Road Recycled Water Storage Pond site. The North Trumble Recycled Water Storage Pond component of the project would be approximately 1,250 ft wide by 1,250 ft long with a depth of approximately 60 ft, with a storage capacity of 297.4 million gallons (913.4 acre ft). The Case Road Recycled Water Storage Pond component of the project would max the utilization of recycled water by providing discharge pipeline and various equipment to increase efficiency and measure the available recycled water in storage.
Contact Information
Name
Cedric S. Irving
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency
Phone
Location
Cities
Perris
Counties
Riverside
Cross Streets
Trumble Road, Case Road, Simpson Road
State Highways
Hwy 74 and 79
Railways
BNSF
Airports
Perris Valley
Schools
Winchester
Waterways
San Jacinto River and Salt Creek
Other Location Info
Winchester
Notice of Determination
Approving Agency
State Water Resources Control Board
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.