Idyllwild Water District (District); Tertiary Recycled Water System (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-7808-110
3 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2010081032
- Lead Agency
- Idyllwild Water District
- Document Title
- Idyllwild Water District (District); Tertiary Recycled Water System (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-7808-110
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 4/29/2015
- Present Land Use
- Rural/Vacant -Riverside Extended Mountain Area Plan
- Document Description
- The pipeline route would be located partially within the public right-of-way and partially through private property, travel on the north side of Strawberry Creek and terminate at the water storage tank in the Idyllwild Pines Campground. The pipeline would begin at the WWTP, travel onto Tollgate Road, Delano Drive, cross utility easements parallel to and on the north side of Strawberry Creek, goes northeast onto Pine Crest Avenue, and connect to the water storage tank in the Idyllwild Pines Campground.
- Contact Information
-
Carina Gaytan
State Water Resources Control Board
1001 I Street 16th Floor
Sacramento, CA 95814
Phone : (916) 327-9401
Location
- Coordinates
- 33°.74'002"N 116°.71'.891"W
- Counties
- Riverside
- Cross Streets
- Lower Pine Crest Drive/State Highway 243
- Zip
- 92549
- Total Acres
- 150
- Parcel #
- 557-120-002
- State Highways
- Hwy 243
- Township
- 5S
- Range
- 2W
- Section
- 14
- Base
- SBB&M
- Other Location Info
- City/Nearest Community: Idyllwild
Notice of Determination
- Approving Agency
- State Water Board
- Approving Agency Role
- Responsible Agency
- Approved On
- Final Environmental Document Available at
- State Water Board, 1001 I Street, 16th Floor, Sacramento, CA 95814
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- No
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.