Guava Street Improvements
3 Documents in Project
Summary
SCH Number
2010081007
Lead Agency
City of Murrieta
Document Title
Guava Street Improvements
Document Type
NOD - Notice of Determination
Received
Posted
1/18/2011
Present Land Use
Present Land Use: Guava Street. The actual project study area is a roadway that does not have specific designation.
Document Description
The City proposes to construct street improvements on Guava Street from Jefferson Avenue to the proposed Guava Street Bridge at Murrieta Creek. Additional street improvements will be necessary on Adams Avenue to accommodate the revised vertical alignment of Guava Street. The project will include the Riverside County Flood Control District design of Line D under Guava Street and Adams Avenue to ultimately discharge into Murrieta Creek. The project will also include three pipe inlets which would convey local runoff from undeveloped areas and curb inlets at the intersection of Guava Street and Adams Ave, which would filter local roadway runoff and trap debris and pollutants prior to the discharge point at Murrieta Creek.
Contact Information
Name
Jeff Hitch
Agency Name
City of Murrieta
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Murrieta
Counties
Riverside
Cross Streets
Along Guava St. from Jefferson Ave to Murrieta Creek
Zip
92562
Total Acres
4
Parcel #
Various
State Highways
I-5 and I-215
Schools
HS, MS, ES
Waterways
Murrieta Creek, Warm Springs Creek
Township
7S
Range
3W
Section
21,28
Notice of Determination
Approving Agency
City of Murrieta
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.