Cordova High School Measure N Modernization and New Construction

2 Documents in Project

Summary

SCH Number
2010072062
Lead Agency
Folsom Cordova Unified School District
Document Title
Cordova High School Measure N Modernization and New Construction
Document Type
NOD - Notice of Determination
Received
Posted
9/27/2010
Present Land Use
Existing public school site zoned RD-5; General Plan designated Public/Quasi-Public
Document Description
Phased new construction and modernization activities projected through the year 2014 and beyond, depending on funding. The major components include remodeling of existing buildings, relocation of and removal of portables once new classrooms are constructed, a new performing arts building, cafeteria remodel, construction of a new auxiliary gym, site work, stadium improvements, on-site circulation routes and parking lot improvements, and utility extensions.

Contact Information

Name
Matt Washburn
Agency Name
Folsom Cordova Unified School District
Contact Types
Lead/Public Agency

Location

Cities
Rancho Cordova
Counties
Sacramento
Cross Streets
2239 Chase Drive North of Coloma Road
Zip
95670
Total Acres
51
Parcel #
056-023-007, -008, -015 and -016
State Highways
Hwy 50
Railways
RT Light Rail
Waterways
American River
Township
9N
Range
6E
Section
27
Base
MDB&M

Notice of Determination

Approving Agency
Folsom Cordova USD
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print