Photovoltaic Cell Panel Installation

3 Documents in Project

Summary

SCH Number
2010071084
Lead Agency
California Department of Transportation, District 5
Document Title
Photovoltaic Cell Panel Installation
Document Type
NOD - Notice of Determination
Received
Posted
11/29/2010
Present Land Use
Santa Cruz-commercial San Luis Obispo-Commercial Buellton-Commercial Santa Barbara-Commercial
Document Description
Caltrans proposes to install solar panels on four State-owned buildings within Santa Cruz, San Luis Obispo, and Santa Barbara counties. In Santa Cruz, approximately 1670sf of solar panels will be mounted to the roof of the Pole Barn (also known as Building E) at the Maintenance Station (APN 026-021-21). Approximately 7920sf of solar panels will be mounted on roof of the Carport within the San Luis Obispo office complex (APN 004-511-020). At the Buellton Santa Barbara Maintenance Station, approximately 1925sf of solar panels will be mounted to the roof of Building F (APN 099-300-002). Approximately 2500 sq of solar panels will be mounted on the maintenance building at the Buellton Maintenance Station.

Contact Information

Name
Jason Wilkinson
Agency Name
California Department of Transportation, District 5
Contact Types
Lead/Public Agency

Location

Cities
Buellton, San Luis Obispo, Santa Barbara, Santa Cruz
Counties
San Luis Obispo, Santa Barbara, Santa Cruz

Notice of Determination

Approving Agency
Caltrans
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.