Engineering Geotechnical Studies for the Bay Delta Conservation Plan and/or Preliminary Engineering Studies for the Delta Habitat Conservation and Conveyance Pr
11 Documents in Project
Summary
SCH Number
2010062041
Lead Agency
California Department of Water Resources
(DWR)
Document Title
Engineering Geotechnical Studies for the Bay Delta Conservation Plan and/or Preliminary Engineering Studies for the Delta Habitat Conservation and Conveyance Pr
Document Type
NOD - Notice of Determination
Received
Posted
9/20/2010
Document Description
The project is limited to ~80 overwater borings, approximately 220 paired geotechnical borings, cone penetrometer soundings, and ~30 small test pits to test soils to obtain geotechnical data. 50 overwater geotechnical borings will take place in the Sacramento River to obtain information for 5 proposed intake structures. Approximately 20 overwater borings are planned at 12 major water crossings. An additional 5 to 12 geotechnical borings are proposed to obtain information for docking facilities. The depths of the borings will range between 100 and 200 ft deep below the bottom of the river and the diameter of the borings will be 3.5 to 5.5 inches. Drilling will be conducted with a rotary drilling rig mounted on a shallow-draft barge or ship. Multiple barges/ships may be operated concurrently. Upon completion of each hole, the borings will be grouted from the bottom of the borehole to within 10-15 ft of the top of the hole with 5% by weight bentonite and 95% by weight cement grout. The project is located throughout the Sacramento-San Joaquin Delta in the Counties of Sacramento, Yolo, San Joaquin, Contra Costa, and Solano.
Contact Information
Name
Andrea Boertien
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Counties
Contra Costa, Sacramento, San Joaquin, Solano, Yolo
Parcel #
Various
State Highways
Hwy 4, 5, 12, 160, 220
Waterways
Various
Section
Multi
Other Location Info
City/Nearest Community: Sacramento-San Joaquin Delta
Notice of Determination
Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.