OPDE US CORP. Conditional Use Permit

2 Documents in Project

Summary

SCH Number
2010062026
Lead Agency
West Sacramento, City of (City of West Sacramento)
Document Title
OPDE US CORP. Conditional Use Permit
Document Type
NOD - Notice of Determination
Received

Document Description
The project consists of a 24 megawatt solar power plant to be located adjacent to and east of the Deep Water Ship Channel navigation levee on land leased from the Port of West Sacramento. Approximately 1,920 single axis trackers would be installed over four approximately forty-acre sites. Each tracker would have approximate dimensions of 23 feet by 46 feet with a maximum height of +/- 15 feet. Each tracker would be mounted on a concrete base. Fill is proposed to bring each site up to a 27-foot elevation. The sites would be interconnected via overhead wires with each site individually connected via underground wires. The new overhead wires would connect to existing overhead lines north of the project site that cross the Deep Water Ship Channel and tie into an existing PG&E substation located at 3000 Ramco St.

Contact Information
David W. Tilley
City of West Sacramento
1110 W. Capitol Avenue, 2nd Floor
West Sacramento, CA 95691

(916) 617-4645

Location

Coordinates
38°32'0.65"N 121°35'13.05"W
Cities
West Sacramento
Counties
Yolo
Zip
95691
Total Acres
160+/-
Parcel #
Various
State Highways
84, 50
Railways
No
Airports
No
Schools
Bridgeway Island Elem.
Waterways
Sacramento River, Sacramento River Deep Water Ship
Township
8N
Range
3E
Section
13

Notice of Determination

Approving Agency
City of West Sacramento
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
City of West Sacramento 1110 West Capitol Avenue West Sacramento, CA 95691

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search