San Bernardino Supply Line Replacement
2 Documents in Project
Summary
SCH Number
2010061085
Lead Agency
City of Riverside
Document Title
San Bernardino Supply Line Replacement
Document Type
NOD - Notice of Determination
Received
Posted
8/12/2010
Document Description
The project is the replacement of an existing, failing 42-inch underground potable water pipeline with a new 48-inch pipeline in an adjacent, disturbed alignment. The existing and proposed pipelines are City of Riverside Public Utilities infrastructure. The project alignment would pass through the cities of Colton and Grand Terrace, in the County of San Bernardino. Total length of the proposed alignment would be approximately 6,600 feet or 1.25 miles. The existing pipeline, which was built in 1926, requires immediate replacement due to several recent leaks, likely caused by seismic activity in the region, and age of the infrastructure. The proposed pipeline would be constructed via trench and jack and bore construction methods.
Contact Information
Name
Blake Yamamoto
Agency Name
City of Riverside Public Utilities District
Contact Types
Lead/Public Agency
Phone
Location
Cities
Colton, Grand Terrace
Counties
San Bernardino
Cross Streets
Washington Street, Mt. Vernon Ave
Zip
92324
Total Acres
2.1
Parcel #
Various
State Highways
I-215
Railways
Union Pacific Railroad
Schools
Terrace View, Cooley Ranch & Wilson Elem.
Waterways
Santa Ana River
Township
1S
Range
5W
Base
SB
Notice of Determination
Approving Agency
City of Riverside
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No