University City High School Athletic Facilities Improvement Project

2 Documents in Project

Summary

SCH Number
2010061049
Lead Agency
San Diego Unified School District
Document Title
University City High School Athletic Facilities Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
9/15/2010
Present Land Use
General Plan Land Use Designation: Institutional & Public and Semi-Public Facilities Zoning: RS (Residential-Single Unit)
Document Description
The proposed project is Phase 1 of the multi-phase improvement project proposed by the District. Phase 1 entails the installation of artificial turf within the approximately 4.5-acre stadium to accommodate football, soccer, and field hockey events. This artificial turf would replace the existing grass field. In addition, the project proposes to replace the existing dirt track surface with a synthetic track. Stadium lighting, a scoreboard, and an upgraded sound system are also proposed as improvements to the facility.

Contact Information

Name
James H. Watts
Agency Name
San Diego Unified School District
Contact Types
Lead/Public Agency

Location

Cities
San Diego
Counties
San Diego
Cross Streets
Genesee Avenue and Centurion Square
Zip
92122
Total Acres
4.5
State Highways
Hwy 5, 805, 52
Railways
BNSF
Airports
MCAS Miramar
Schools
University City HS, Curie Elem. Standly Middle School, Spreckler
Other Information
Schools Cont. Doyle Elem, La Jolla County Day School, UC San Diego

Notice of Determination

Approving Agency
San Diego Unified School District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print