Hennessey Creek Modification Project

2 Documents in Project

Summary

SCH Number
2010052061
Lead Agency
Fairfield, City of (City of Fairfield)
Document Title
Hennessey Creek Modification Project
Document Type
NOD - Notice of Determination
Received

Document Description
The proposed Hennessey Creek Modification project would construct a creek diversion channel and settling basin immediately north of Reservoir Lane in Solano County to replace the existing Hennessey Creek bypass pipes. A parcel immediately north of Reservoir Lane has experienced flooding on a more regular basis after the bypass of Hennessey Creek to Green Valley Creek was constructed south of Reservoir Lane in 1993. The proposed project resulted from a settlement reached in a lawsuit filed by adjacent property owners against the City of Fairfield. The proposed project would also include the installation of a box culvert overflow structure underneath Reservoir Lane to connect the settling basin with Green Valley Creek; and new rock slope protection from the southerly side of Reservoir Lane to the top of the Green Valley Creek bank.

Contact Information
Joe Lucchio
City of Fairfield
1000 Webster Street
Fairfield, CA 94533

707-428-7647

Location

Coordinates
38°13'35"N 122°09'12"W
Cities
Fairfield
Counties
Solano
Cross Streets
Reservoir Ln, Green Valley Rd
Zip
94534
Total Acres
1.6
Parcel #
0148-190-007
State Highways
12
Railways
SPRR
Schools
Nelda Mundy ES
Waterways
Hennessey Creek, Green Valley Creek, Jameson Canyon Creek
Township
4N
Range
3W
Section
1,2
Base
Cord 7.5

Notice of Determination

Approving Agency
City of Fairfield
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
City of Fairfield 1000 Webster St Fairfield, CA 94533

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search