Placer County Regional Transportation Plan 2010-2035

3 Documents in Project

Summary

SCH Number
2010052013
Lead Agency
Placer County
Document Title
Placer County Regional Transportation Plan 2010-2035
Document Type
NOD - Notice of Determination
Received
Posted
9/22/2010
Present Land Use
GPLUD & Zoning of Placer County, Auburn, Colfax, Lincoln, Loomis, Rocklin, and Roseville.
Document Description
The Placer County 2035 Regional Transportation Plan (RTP) documents the policy direction, actions, and funding recommendations intended to meet the short and long range needs of Placer County's transportation system over the next 25 years. The RTP is designed to guide the systematic development of a balanced, comprehensive, multi-modal transportation system. The RTP fulfills state requirements of AB 402, CTC guidance, including the 2010 TRP Guidelines, federal planning requirements and CEQA.

Contact Information

Name
David Melko
Agency Name
Placer County Transportation Planning Agency
Contact Types
Lead/Public Agency

Location

Cities
Auburn, Auburn, Colfax, Lincoln, Loomis, Rocklin, Roseville, ..., Colfax, Lincoln, Loomis, Rocklin, Roseville
Counties
Placer
Regions
Countywide, Unincorporated
Cross Streets
Countywide
Zip
various
Total Acres
898,820
Parcel #
various
State Highways
Hwy 20,28,49,65,80,89,174,192...
Railways
Capitol Corridor, UPRR
Airports
Auburn, Blue Canyon, Lincoln
Schools
Various
Waterways
Donner, Folsom, French, Hell Hole & Lake Tahoe

Notice of Determination

Approving Agency
Placer County Transportation Planning Agency (PCTPA)
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print