Uptown Newport Village Specific Plan Project
5 Documents in Project
Summary
SCH Number
2010051094
Lead Agency
City of Newport Beach
Document Title
Uptown Newport Village Specific Plan Project
Document Type
NOD - Notice of Determination
Received
Posted
3/1/2013
Present Land Use
LU: Z: GP: Industrial: Koll Center Planned Community (PC-15): Mixed Use Horizontal-2 (MU-H2)
Document Description
The proposed Uptown Newport project would consists of mixed uses with up to 1,244 residential units, 11,500 sf of neighborhood-serving retail space, and ~two acres of park space. Proposed buildings would range from 30 feet to 75 feet in height; with residential towers up to 150 feet high (13 stories). Residential product types would be for-sale products with a mix of townhomes, mid-and high-rise condominiums, and affordable housing. In addition to neighborhood-serving retail, the vision for the project is to incorporate an upscale, sit-down restaurant within the 11,500 sf commercial development. Two parks totaling ~2 acres would be developed, as well as landscaped area surrounding proposed buildings. Parks and landscaped areas would be accessible to the public but privately owned. Access to the site would be from Jamboree Road, Birch Street, and Von Karman Avenue.
Contact Information
Name
Rosalinh Ung
Agency Name
City of Newport Beach
Contact Types
Lead/Public Agency
Phone
Email
Location
Coordinates
Cities
Newport Beach
Counties
Orange
Cross Streets
Jamboree Road and Fairchild Road
Zip
92660
Total Acres
25.09
State Highways
I-405, SR-55, SR-73
Airports
John Wayne Airport
Schools
5 private/Parochial Schools/1 public ES
Waterways
San Diego Creek, Barranca Channel, Upper Newport Bay
Township
6S
Range
9W
Section
7
Base
SBB&M
Notice of Determination
Approving Agency
City of Newport Beach
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.