Fairfield Train Station Specific Plan (Adopting Amendments to the Vacaville-Fairfield-Solano Greenbelt)

16 Documents in Project

Summary

SCH Number
2010042093
Lead Agency
City of Fairfield
Document Title
Fairfield Train Station Specific Plan (Adopting Amendments to the Vacaville-Fairfield-Solano Greenbelt)
Document Type
NOD - Notice of Determination
Received
Posted
10/28/2011
Present Land Use
agriculture, parks and recreation, open space, public/quasi-public, industrial, office, community commercial, residential, etc.
Document Description
The focal point of the Specific Plan is the approved Capitol Corridor train station at the intersection of Peabody and Vanden Road. The Specific Plan provides for a minimum of 3,000 dwelling units within a one-half mile radius of the station. At buildout, the Specific Plan could accommodate up to an additional 6,800 dwelling units, an added population of ~19,277, roughly 5 million sf of commercial and industrial development, and a range of public and open space uses on ~2,972 acres of land.

Contact Information

Name
David Feinstein
Agency Name
Vacaville-Fairfield-Solano Greenbelt JPA
Contact Types
Lead/Public Agency

Location

Cities
Fairfield
Counties
Solano
Cross Streets
Intersection of Peabody and Vanden Road
Zip
94533
Total Acres
2,972
Parcel #
Various
State Highways
Hwy 12
Railways
UPRR
Airports
Travis AFB
Schools
Vanden HS, Center ES
Waterways
Union Creek, McCoy Creek

Notice of Determination

Approving Agency
Vacaville-Fairfield-Solano Greenbelt Joint Powers Authority
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.