South Bay Bus Rapid Transit

9 Documents in Project

Summary

SCH Number
2010041060
Lead Agency
San Diego Association of Governments
Document Title
South Bay Bus Rapid Transit
Document Type
NOD - Notice of Determination
Received

Document Description
SANDAG has adopted an Addendum to the Final Environmental Impact Report (EIR) for the South Bay Bus Rapid Transit Project to address changes since initial approval of the project and certification of the Final EIR on July 26, 2013. The project changes include modifying a traffic signal to change the outbound access from a shopping center's mid-block driveway to right-turn out only, acquiring property in order to relocate a fiber optic facility, and making other related physical improvements. The proposed changes are located along East Palomar Street between Medical Center Drive/Brandywine Avenue and Davies Drive in the City of Chula Vista. SANDAG has determined that the project changes do not create any of the conditions in CEQA Guidelines 15162 requiring preparation of a Subsequent EIR and therefore has adopted an Addendum pursuant to 15164.

Contact Information
Andrew Martin
San Diego Association of Governments
401 B Street, Suite 800
San Diego, CA 92101

619-595-5375

Location

Cities
San Diego National City Chula Vista
Counties
San Diego
Cross Streets
between Otay Mesa Port of Entry & Downtown San Diego
Zip
92101
Total Acres
21 mile segment
Parcel #
primarily public right-of-ways
State Highways
SR 94, 125, 905 & I-805
Railways
AT&SF (MTS)
Airports
San Diego Int'l
Schools
Various
Waterways
Various

Notice of Determination

Approving Agency
San Diego Assocation of Governments (SANDAG)
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
SANDAG, 401 B Street, Suite 800, San Diego, CA 92101

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
Yes
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search