Jurupa Avenue Extension from Rutland Avenue to Hole Lake Dam/Crossing (EPW-10-001)

3 Documents in Project

Summary

SCH Number
2010041010
Lead Agency
City of Riverside
Document Title
Jurupa Avenue Extension from Rutland Avenue to Hole Lake Dam/Crossing (EPW-10-001)
Document Type
NOD - Notice of Determination
Received
Posted
2/9/2011
Document Description
CDFG is executing Lake and Streambed Alteration Agreement (SAA # 1600-2010-0116-R6) pursuant to Section 1602 of the Fish and Game Code to the project Applicant: City of Riverside, represented by Ed Lara, 3900 Main Street, City of Riverside, State of CA, 92522, Phone (951) 826-2337. The project is limited to the extension of Jurupa Avenue from 610 feet west of Van Buren Boulevard to Rutland Avenue and associated street improvements, and the reconstruction of the Hole Lake Dam and associated infrastructure. The reconstruction of the Hole Lake Dam will include the removal of the existing concrete spillways, removal and replacement of the existing culvert draining the Hole Lake area, and construction of two 12-foot diameter culverts that will parallel the existing pipeline alignment.

Contact Information

Name
Edward Lara
Agency Name
CA Department of Fish and Game Inland Deserts Region 6
Contact Types
Lead/Public Agency

Location

Cities
Riverside
Counties
Riverside
Cross Streets
Rutland Ave / Van Buren Blvd
Zip
92503
Total Acres
4.65
State Highways
No
Railways
UPRR
Airports
Riverside Municipal
Schools
Norte Vista HS,Terrace,La Granada,Arlanza,Wells Middle Foothill
Waterways
Santa Ana River
Township
2S
Range
4W
Section
36
Other Information
Schools continued: Jackson, Adams, Rose Kennedy ES, Rehoboth Charter, Harvest Christian

Notice of Determination

Approving Agency
CDFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.