Port of Oakland Maritime Utilities Upgrade Project

6 Documents in Project

Summary

SCH Number
2010032100
Lead Agency
Oakland, Port of (Port of Oakland)
Document Title
Port of Oakland Maritime Utilities Upgrade Project
Document Type
NOD - Notice of Determination
Received

Document Description
This phase of the project consists of approving the draft and final project plans and project manual for the first three berths in the Shore Power Program (Berths 56-58); advertising for construction bids, resolving and bid protests, and awarding and executing the construction contract for shore power infrastructure at berth 56-58. The Port's Maritime Utilities Upgrade Project, as described in the Initial Study/Negative Declaration, consists of two elements: 1. The phased construction and operation of shore power improvements at the Port's marine terminals to reduce air quality impacts from engines of ships at berth, in compliance with California Air Resources Board (CARB) regulations. The system would consist of either an electrical grid-based power source, transmissions system, and related power distribution system or an on-site power generation system; and 2. The design-build and operation of a perimeter intrusion detection security system on and at the perimeter of the marine terminals, in order to improve security at the Port.

Contact Information
Anne M. Whittington
Port of Oakland
530 Water Street
Oakland, CA 94607

510-627-1559

Location

Coordinates
37°48'20"N 122°19'07"W
Cities
Oakland
Counties
Alameda
Cross Streets
Middle Harbor Rd and 7th St
Zip
94607
Total Acres
~800
Railways
BNSF, UPRR
Waterways
SF Bay

Notice of Determination

Approving Agency
Board of Port Commissions of the Port of Oakland
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
Port of Oakland Environmental Programs and Planning Division 530 Water Street Oakland, CA 94607

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
No
Download CSV New Search