Orchard at Penryn Project (Lake or Streambed Alteration Agreement No. 1600-2014-0162-R2)

7 Documents in Project

Summary

SCH Number
2010032070
Lead Agency
Placer County
Document Title
Orchard at Penryn Project (Lake or Streambed Alteration Agreement No. 1600-2014-0162-R2)
Document Type
NOD - Notice of Determination
Received
Posted
1/22/2015
Present Land Use
Undeveloped/RM-DL10 PD = 10 & C1-UP-DC / Penryn Parkway

Document Description
The California Department of Fish and Wildlife (CDFW) has executed Lake and Streambed Alteration Agreement number 1600-2014-0162-R2, pursuant to section 1602 of the Fish and Game Code to the project Applicant, Penryn Development, LLC. The project is limited to three separate work areas within the Orchard at Penryn Project development area that includes work within unnamed seasonal wetland swales and intermittent drainages which are tributaries to Secrete Ravine. The purpose of these three project features are: to complete clearing, grading, and site remediation of contaminated soils onsite; install a 30-inch diameter pipe along an intermittent drainage; and install a 60-inch diameter pipe along the eastern wetland swale/intermittent stream system.

Contact Information
Patrick Moeszinger
CDFW North Central Region
1701 Nimbus Road
Rancho Cordova, CA 95670

Phone : (916) 358-2850

Location

Coordinates
38°50'20.3"N 121°10'14.5"W
Counties
Placer
Cross Streets
Penryn Road
Total Acres
15.1
Parcel #
043-060-052, 053
State Highways
I-80
Township
11N
Range
7E
Section
2
Base
MDB&M
Other Location Info
City/Nearest Community: Penryn

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
CDFW North Central Region, 1701 Nimbus Road, Rancho Cordova, CA 95670

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes