Powerhouse Science Center (P10-014)
5 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2010032067
- Lead Agency
- Sacramento, City of (City of Sacramento)
- Document Title
- Powerhouse Science Center (P10-014)
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 6/2/2010
- Document Description
- The Powerhouse Science Center project proposes to develop the northern half of the R.T. Matsui Waterfront Park, which is approximately 6.35 of undeveloped land; rehabilitate the former PG&E Power Station; and , construct new facilities at the to accommodate the Sacramento Museum of History, Science and Technology (SMHT). The Project includes the following: Amendment of the Master Plan for the Robert T. Matsui Waterfront Park to reflect the uses proposed for the Project Site and redesignation as a community park. Improvements to the Park, including additional surface parking, rebuilding the promenade and main lawn, and installation of play and art structures, and sound and shade structures; Rehabilitation of the former PG&E Power Station B building to serve as the Powerhouse Science Center; A Planetarium and Challenger Center would be constructed; Education Center and Restaurant; On-site parking with a two story parking structure and surface level parking lots; and, Development of two "Living Machine" waste-water reuse systems.
- Contact Information
-
Dana Allen
City of Sacramento
300 Richards Boulevard
Sacramento, CA 95811
Phone : (916) 808-2762
Location
- Cities
- Sacramento
- Counties
- Sacramento
- Cross Streets
- Jibboom St
- Total Acres
- 6.35
- Parcel #
- various
- State Highways
- I-5
- Railways
- UPRR
- Waterways
- Sacramento and American Rivers
Notice of Determination
- Approving Agency
- City of Sacramento
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- City of Sacramento, Development Services Department 300 Richards Boulevard, Third Floor Sacramento, CA 95811
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.