Claremont Colleges East Campus

6 Documents in Project

Summary

SCH Number
2010021040
Lead Agency
City of Upland
Document Title
Claremont Colleges East Campus
Document Type
NOD - Notice of Determination
Received
Posted
6/2/2016
Present Land Use
Upland: Class III Landfill/SP/I, Claremont: Archery Range, temporary Parking, Class III Landfill/IE/Institutional
Document Description
The proposed Project consists of a subdivision, master site plan, site plan, and development agreement for the phased development of a college sports complex with recreation/athletic fields, sports, parking, and supporting building facilities on a 75-acre former aggregate quarry. Existing land uses include an archery range and a temporary construction parking area adjacent to Claremont Boulevard in addition to a permitted Class III landfill site. The purpose of the phased development is the relocation of sports facilities and associated parking from the main college campuses to the former quarry site and to provide additional parking for the campuses. The Draft EIR is being Recirculated as a result of changes to the conceptual site plan. The development of two additional sports fields is now being considered; however, the total site acreage remains unchanged.

Contact Information

Name
Jerry Guarracino
Agency Name
City of Upland
Contact Types
Lead/Public Agency

Location

Cities
Claremont, Upland
Counties
Los Angeles, San Bernardino
Cross Streets
Foothill Boulevard at Claremont Boulevard
Zip
91786...
Total Acres
~75
Parcel #
1007-011-01, 8308-025-012
State Highways
Hwy 66
Railways
SPRR
Airports
Cable Airport
Schools
Multiple
Waterways
San Antonio Creek
Township
1S
Range
8W
Section
10
Base
SBB&M

Notice of Determination

Approving Agency
City of Upland
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print