Interstate 805 North Managed Lanes; 1600-2011-0179-R5

5 Documents in Project

Summary

SCH Number
2010021032
Lead Agency
California Department of Transportation, District 11
Document Title
Interstate 805 North Managed Lanes; 1600-2011-0179-R5
Document Type
NOD - Notice of Determination
Received
Posted
10/24/2011
Document Description
The Department of Fish and Game is executing a Streambed Alteration Agreement pursuant to Fish and Game Code section 1602 to the project applicant; Caltrans District 11. The project is limited to construction of four 12-foot wide managed lanes, two in each direction, with a four foot buffer area on each side, in the median of I-805 from SR-52 to just north of the La Jolla Village Drive and one High Occupancy Lane (HOV) from just north of the La Jolla Village Drive to just north of Mira Mesa Blvd., with widening of the outside portion of the roadway to accommodate the additional lanes. Additionally, the project will include a direct connector ramp at SR-52/I-805, a direct access ramp (DAR) at Carroll Canyon, a DAR at Nobel Drive, and a park and ride/transit station at the southwest quadrant of Nobel and I-805. The project crosses three main canyons and several drainages.

Contact Information

Name
Tim Dillingham
Agency Name
DFG, South Coast Region
Contact Types
Lead/Public Agency

Location

Cities
San Diego
Counties
San Diego
Cross Streets
SR 52 and Mira Mesa Blvd
Zip
92121
State Highways
SR 52, I-5
Railways
MTS
Airports
MCRD

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.