Holder Interim School Project

2 Documents in Project

Summary

SCH Number
2010021025
Lead Agency
Savanna School District
Document Title
Holder Interim School Project
Document Type
NOD - Notice of Determination
Received
Posted
4/5/2010
Document Description
The proposed project includes the installation of 17 interim classrooms and 7 permanent classrooms and support facilities (rest rooms, staff room, etc.). The facilities construction within the Holder School campus will accommodate the individual enrollments from the 3 other SAVSD schools as well as the Holder School itself, while they individually undergo improvement. Students from each of these other schools will attend the Holder Interim School while their respective schools undergo modernization. The individual school modernization will take one year to complete for each school for a combined total construction period of three years. Once the construction for the other schools has been completed, the Holder School students will be relocated to the 17 interim modular classrooms and 7 new permanent classrooms while the Holder School campus undergoes modernization. When the entire modernization program is completed, the interim improvements will be removed.

Contact Information

Name
Lynne Merrick
Agency Name
Savanna School District Administrative Office
Contact Types
Lead/Public Agency

Location

Cities
Buena Park
Counties
Orange
Cross Streets
Orange Ave. and Holder St.
Zip
92804
Total Acres
10+
State Highways
SR39, I-605, and SR-22
Railways
Southern
Airports
Los Alamitos
Schools
Holder Elementary School
Waterways
Carbon Creek

Notice of Determination

Approving Agency
SAVSD
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.