Lake Forest Water Company Acquisition and Water System Reconstruction

5 Documents in Project

Summary

SCH Number
2010012067
Lead Agency
Tahoe City Public Utility District
Document Title
Lake Forest Water Company Acquisition and Water System Reconstruction
Document Type
NOD - Notice of Determination
Received

Document Description
The project includes the acquisition of the assets of the Lake Forest Water Company by the TCPUD and reconstruction of the water system within the Lake Forest Water Improvement District service area to meet California Waterworks Standards and the California Fire Code. TCPUD would assume opertaion and maintenance responsibilities for the water system within the LFWID area. Approximately 2,500 lineal ft (LF) of 12 inch PVC water main and ~8,050 LF of 8 inch PVC water marina would be installed in roadways and shoulders to replace the existing water system in the area. Water meter boxes and service laterals would be installed to individual parcels and 26 fire hydrants would be installed with the project.

Contact Information
Matt Homolka
Tahoe City Public Utility District
P.O. Box 5249
Tahoe City, CA 96145

530-583-3796

Location

Coordinates
39°11'1.66"N 120°6'47.37"W
Counties
Placer
Cross Streets
Lake Forest Rd
Zip
96145
Total Acres
~1
Parcel #
multiple, Placer County right of way
State Highways
28
Schools
North Tahoe HS, Tahoe Lake ES
Waterways
Lake Tahoe, Lake Forest Creek, Polaris Creek, Burton Creek
Township
15,16N
Range
17E
Section
4,5,32
Base
Kngs Bch
Other Location Info
City/Nearest Community: Tahoe City

Notice of Determination

Approving Agency
Tahoe City Public Utility District
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
Tahoe City Public Utility District 221 Fairway Drive Tahoe City, CA

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes