Caltrans Modesto Soil Stockpiles State Route 132 West Freeway/Expressway Project

7 Documents in Project

Summary

SCH Number
2010012010
Lead Agency
Caltrans 6 (Fresno) (California Department of Transportation, District 6)
Document Title
Caltrans Modesto Soil Stockpiles State Route 132 West Freeway/Expressway Project
Document Type
NOD - Notice of Determination
Received

Document Description
Project consists of containment of three stockpiles totaling approx. 160,000 cubic yards of soil containing metals (primarily barium, strontium, and lead) during construction of the SR 132 West Freeway/Expressway Project. The DTSC has approved the Remedial Action Plan for the Caltrans Modesto Soil Stockpiles SR 132 West Freeway/Express Site. The stockpiles occupy three areas within the state right-of-way located south of Kansans Avenue: between Carpenter Avenue and East Emerald Avenue, Emerald Avenue and SR 99. The stockpiles will be contained behind retaining walls, bridge abutments, and beneath the roadway. Unpaved portions will have clean fill cover. This containment remedy provides long-term protection of people and the environment by preventing exposure and minimizing the infiltration of surface water into groundwater under the stockpiles. Land use controls and inspection of the pavement and other features of the containment remedy and groundwater monitoring will be conducted annually to ensure the integrity of the remedy into the future.

Contact Information
Randy Adams
DTSC
8800 Cal Center Dr.
Sacramento, CA 95826

916-255-3591

Location

Coordinates
37°38'20"N 121°0'25"W
Cities
Modesto
Counties
Stanislaus
Cross Streets
State Route 99, SR 132
Zip
95351
Total Acres
238.25
State Highways
Hwy 132, 99
Airports
Modesto Co, Mapes & Yandell
Schools
several
Waterways
Tuolumne River

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
8800 Cal Center Dr., Sacramento, CA 95826

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes