ESJ US Generation - Tie Line Major Use Permit; 3300-09-008 (MUP), 3910-99-22-001 (ER)
11 Documents in Project
Summary
SCH Number
2009121079
Lead Agency
California Public Utilities Commission
(CPUC)
Document Title
ESJ US Generation - Tie Line Major Use Permit; 3300-09-008 (MUP), 3910-99-22-001 (ER)
Document Type
NOD - Notice of Determination
Received
Posted
6/27/2012
Present Land Use
Undeveloped
Z: General Rural, Open Space, Specific Plan, Agriculture, Indian Reservation
GPD: Multiple Rural Use (1 DU/4, 8, 20 AC), Public/Semi-Public Lands, Specific Plan Area, General Agriculture, Indian Reservation
Document Description
San Diego Gas & Electric is proposing to construct and operate a new 500/230/138-kilovolt (kV) substation, a new 13.3-mile 138kV transmission line, and would rebuild the existing Boulevard Substation to operate at 138/69/12 kV.
Contact Information
Name
Amy Baker
Agency Name
CA Public Utilities Commission
Contact Types
Lead/Public Agency
Phone
Location
Counties
San Diego
Cross Streets
Old Highway 80, Carrizo Gorge Road, Tule Jim Lane, Highway 94, McCain Valley Rd, Ribbonwood Rd
Zip
Multiple
Parcel #
Multiple
State Highways
I-8, SR-94
Railways
San Diego and Arizona Eastern
Airports
Jacumba
Schools
Clover Flat Elementary, Jacumba Elementary
Waterways
Multiple
Township
Multip
Section
Multip
Base
Multiple
Other Location Info
City/Nearest Community: Jacumba/Boulevard
Other Information
Schools: Mountain Empire Unified School District
Notice of Determination
Approving Agency
CA Public Utilities Commission
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes