Main Wastewater Treatment Plant Land Use Master Plan - Minor Modifications to the Modified Food Waste Project as Described int the FEIR and the June 2015 Modifi

14 Documents in Project

Summary

SCH Number
2009112073
Lead Agency
East Bay Municipal Utility District (EBMUD)
Document Title
Main Wastewater Treatment Plant Land Use Master Plan - Minor Modifications to the Modified Food Waste Project as Described int the FEIR and the June 2015 Modifi
Document Type
NOD - Notice of Determination
Received
Posted
11/30/2015
Present Land Use
Zoning: Industrial General; General Plan Designation: General Industrial/Transportation
Document Description
The East Bay Municipal Utility District (EBMUD) Main Wastewater Treatment Plant (MWWTP) Land Use Master Plan EIR (LUMP EIR) was prepared and certified in 2011 to serve as a high-level planning tool to guide development of the existing 48-acre MWWTP site and the newly-acquired, adjacent 15.9-acre West End property (former U.S. Army Reserve Center) over a 30-year time horizon. The LUMP EIR identified two renewable energy projects for implementation in the near future- biodiesel production and food waste preprocessing - to help EBMUD meet sustainability goals by increasing on-site power generation. EBMUD has now modified the food waste project (Modified Project). The Modified Project would involve acceptance of organics-rich waste collected from multiple sources, including the City of Oakland in goth unprocessed and preprocessed form, and from other communities within the surrounding area. The Modified Project would also include construct and operation of facilities for food waste processing, urban organics, dedicated digestion and dewatering, and renewable vehicle fuel production. Following EBMUD's June 2015 approval of the Modified Project, certain minor modifications were determined to be necessary, including the addition of a thermal oil heater and clarifications on the height of compressed natural gas facilities to be built as part of the Modified Project. EBMUD analyzed these minor modifications in a subsequent, November 2015 addendum. Based upon the analysis in that addendum, EBMUD determined that no further environmental review was required and approved amendment of a contract for preliminary engineering and design services for the Modified Project, including the minor modifications considered in the November 2015 addendum. This approval is part of the Modified Project, as described in the FEIR and subsequent addenda thereto.

Contact Information

Name
Alicia Chakrabarti
Agency Name
East Bay Municipal Utility District
Contact Types
Lead/Public Agency

Location

Cities
Oakland
Counties
Alameda
Cross Streets
Wake Avenue/West Grand Avenue
Zip
94607
Total Acres
63.9
Parcel #
000-0305-003-03, 000-0305-003-16
State Highways
I-80, 580, 880, 24, 13
Railways
UPRR, BNSF
Airports
No
Waterways
SF Bay

Notice of Determination

Approving Agency
East Bay Municipal Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.