State Route 99 Manteca Widening Project
8 Documents in Project
Summary
SCH Number
2009112045
Lead Agency
California Department of Transportation, District 6
Document Title
State Route 99 Manteca Widening Project
Document Type
NOD - Notice of Determination
Received
Posted
9/16/2010
Document Description
Caltrans proposes to widen SR 99 from the existing 4 lane facility to 6 lanes within the median from the Austin Road interchange in the city of Manteca (PM 4.9) to the Arch Road interchange in the city of Stockton (PM 15.0) by adding two 12 ft lanes in the median and constructing a concrete median barrier. The construction of the project includes the following improvements: Widen bridge structure medians at Lone Tree Creek, South Fork South Littlejohns Creek, and North Fork South Littlejohns Creek. Close existing hook ramp (North Fork South Littlejohns Creek hook ramps) connections south of the Stockton Metropolitan Airport.
Contact Information
Name
Gary L. Hobgood
Agency Name
Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Cities
Manteca
Counties
San Joaquin
Cross Streets
Between Austin Rd interchange in Manteca and Arch Road interchange in Stockton
State Highways
99
Railways
UPRR
Airports
Stockton Metropolitan
Schools
Golden West ES
Waterways
Lone Tree Creek, French Camp SLough, Littlejohns Creek
Notice of Determination
Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.