ND-551-P - 1420 - 1450 Howard Ave. & 249 Park Rd. - Burlingame Safeway Mixed-Use Development Project

2 Documents in Project

Summary

SCH Number
2009112043
Lead Agency
City of Burlingame
Document Title
ND-551-P - 1420 - 1450 Howard Ave. & 249 Park Rd. - Burlingame Safeway Mixed-Use Development Project
Document Type
NOD - Notice of Determination
Received
Posted
2/22/2010
Document Description
The project sponsor proposes to demolish the existing Safeway and Walgreens buildings at the project site. A new Safeway building would be constructed in its place and a new mixed-use buildings would be constructed on the corner of Howard Avenue/Primrose Road. In addition, the existing Wells Fargo building on the corner of Primrose Road/Fox Plaza Lane would be remodeled as part of the proposed project. The 3 buildings on the 150,053 sf sf lot (3.44 acres) would total ~76,277 gsf and would have a combined floor-area-ratio (FAR) of 0.5. The proposed project also includes: 226 total parking spaces; changes to circulation; new landscaping; changes to lighting; a "gateway feature"; and monumental signage.

Contact Information

Name
William Meeker
Agency Name
City of Burlingame Community Development Dept
Contact Types
Lead/Public Agency

Location

Cities
Burlingame
Counties
San Mateo
Cross Streets
Howard Ave/El Camino Real/Primrose Rd
Zip
94010
Total Acres
3.44
Parcel #
029-201-200, 270, 190, 280, 300
State Highways
82, 101
Railways
Caltrain ROW
Airports
No
Schools
Multiple
Waterways
SF Bay
Township
4S
Range
4W
Section
18,19
Base
MDB&M

Notice of Determination

Approving Agency
Burlingame City
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.