Markeley Lane Road Entension Project

3 Documents in Project

Summary

SCH Number
2009112015
Lead Agency
Travis Unified School District
Document Title
Markeley Lane Road Entension Project
Document Type
NOD - Notice of Determination
Received
Posted
5/5/2010
Document Description
The project is located near the intersection of Markeley Lane and De Ronde Drive, Fairfield, Solano County. The project includes the construction of a 1,500-foot long by 36-wide paved roadway with bicycle lanes and a 6-foot wide sidewalk and a 36-foot wide and 20-foot free span pre-cast concrete bridge on Union Creek Bypass Channel. Clean backfill will be placed behind the concrete bridge headwalls and wing walls. The eastern end of the cul-de-sac will be excavated approximately eight feet into the hillside. A storm-water detention basin will also be constructed and will discharge storm-water into the Channel. The basin will have maximum fill of approximately four feet, and a maximum holding time for water of 24 to 36 hours. The California Department of Fish and Game (DFG) is executing a Lake and Streambed Alteration Agreement Number 1600-2009-0336-3 pursuant to Section 1602 of the Fish and Game Code to the project Permittee, Ken Forrest/ Travis Unified School District.

Contact Information

Name
Brenda Blinn
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Fairfield
Counties
Solano
Cross Streets
Peabody Rd and Air Base Parkway
Total Acres
2.88
Parcel #
174-010-010, 050, 310
Township
5N
Range
1W
Section
15

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print