The 2009 Amendment to the Redevelopment Plan for Project Area No. 2, as amended, to extend Agency authority with regard to eminent domain on non-residential pro

2 Documents in Project

Summary

SCH Number
2009101109
Lead Agency
City of Barstow
Document Title
The 2009 Amendment to the Redevelopment Plan for Project Area No. 2, as amended, to extend Agency authority with regard to eminent domain on non-residential pro
Document Type
NOD - Notice of Determination
Received
Posted
8/19/2010
Present Land Use
GP: Neighborhood Residential, Urban Living, Mixed Use, General Commercial, Public and Quasi-Public, Specific Plan
Document Description
The proposed project is an amendment to the Barstow Redevelopment Agency's existing Redevelopment Plans for project Area No. 1, as amended (Amendment Areas No. 1 and 2) and Project Area No. 2, as amended (Amendment Area No. 1). The project is to reinstate the Agency's authority to use the power of eminent domain, if necessary and as a last resort, to acquire non-residential property only within Project Area No. 1, Amendment Area No. 2 (PA 1-2) and Project Area No. 2 (PA 2) and its Amendment Area No. 1 (PA 2-1). The eminent domain powers do not extend to properties that are legally occupied as a residence. Therefore, the amendment only applies to these three areas, PA 1-2, PA 2 and PA 2-1 (Amendment Area), which totals 2,983 acres.

Contact Information

Name
Michael Massimini
Agency Name
City of Barstow Redevelopment Agency
Contact Types
Lead/Public Agency

Location

Cities
Barstow
Counties
San Bernardino

Notice of Determination

Approving Agency
City of Barstow
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes