Cal Poly Meats Processing Center

2 Documents in Project

Summary

SCH Number
2009101078
Lead Agency
California State Polytechnic University, San Luis Obispo
Document Title
Cal Poly Meats Processing Center
Document Type
NOD - Notice of Determination
Received
Posted
8/5/2010
Present Land Use
Outdoor Teaching and Learning, per the Cal Poly Master Plan

Document Description
Cal Poly proposes to relocate Abattoir functions from the campus instructional core to a new location on Stenner Creek Road northwest of the Poultry Science Instructional Center. The project would include grading less than 2 acres of irrigated pasture, construction of a paved entrance and parking area off Stenner Creek Road, and construction of a one-story 14,405 sf building. Water to serve the site would be obtained from an existing City water line located along Stenner Creek Road. Sewer, electrical, gas, and telecom services would be extended to the project site from the existing Poultry Science Instructional Center.

Contact Information
Joel Neel
California State Polytechnic University, San Luis Obispo
1 Grand Avenue
San Luis Obispo, CA 93407

Phone : (805) 756-2193

Location

Coordinates
35°18'52"N 120°40'52"W
Cities
San Luis Obispo
Counties
San Luis Obispo
Cross Streets
Grand Ave, Highland Dr
Zip
93407
Total Acres
2
Parcel #
073-341-023
State Highways
Hwy 1
Railways
UPRR
Schools
Cal Poly
Waterways
Stenner Creek
Township
30S
Range
12E
Section
15
Base
MDB&M

Notice of Determination

Approving Agency
The Trustees
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
Californai State University, California Polytechnic State University Facilities Planning and Capital Project 1 Grand Avenue, Bldg. 70 San Luis Obispo, California 93407

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.