Addendum to the Mitigated Declaration for the Interim Removal Measure Workplan for Ascon Landfill Site

4 Documents in Project

Summary

SCH Number
2009101077
Lead Agency
Department of Toxic Substances Control
Document Title
Addendum to the Mitigated Declaration for the Interim Removal Measure Workplan for Ascon Landfill Site
Document Type
NOD - Notice of Determination
Received
Posted
12/8/2010
Document Description
The proposed Interim Removal Measure (IRM) planned for 2010 at the Ascon Landfill site includes removal and disposal, or, if feasible, recycling of up to ~ 70,000 cubic yards of tarry materials from two interior lagoons in the southwest zone of the Ascon site that received oil production waste during the landfill's operations. The purpose of the IRM is to enable assessment of the material underneath the tarry materials in Lagoons 1and 2. After on-going construction IRM activities within Lagoons 1 and 2, it has been determined that removal of materials from Lagoon3 will be necessary to ensure the stability of the existing berm between Lagoons 2 and 3. In comparison to the IRM activities described in the Final MND and Modified IRM Proposal (analyzed in Addendum No 1), the loading area for the Lagoon 3 Proposal would not be located closer to the site perimeter than existing onsite roads used as part of ongoing IRM activities, the traffic count of haul trucks will not change, off-site haul routes will not change, the construction schedule will not change, and the maximum volume of removable materials during the IRM (70,000 cubic yards) will not be exceeded as stated in the Final MND. Further, the Lagoon 3 Proposal will comply with the same regulatory requirements and implement the same components in the IRM Workplan that serve to minimize impacts on the environment.

Contact Information

Name
Greg Holmes
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Cities
Huntington Beach
Counties
Orange
Cross Streets
Magnolia St and Hamilton Ave
Zip
92646
Total Acres
38
Parcel #
114-150-75, -78, -79, -80
State Highways
Hwy 1, 39
Schools
Edison HS, numerous schools
Waterways
Huntington Beach Flood Control Channel, Santa Ana River
Township
6S
Range
11W
Section
13
Base
SBB&M

Notice of Determination

Approving Agency
Department of Toxic Substances Control
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.