California High Speed Train - Fresno to Bakersfield Permitting Packages 1.a and 1.b

45 Documents in Project

Summary

SCH Number
2009091126
Lead Agency
High Speed Rail Authority, California (California High Speed Rail Authority)
Document Title
California High Speed Train - Fresno to Bakersfield Permitting Packages 1.a and 1.b
Document Type
NOD - Notice of Determination
Received

Document Description
This is the 2nd amendment to the orginal Order. The Project will construct approximately 87 miles of the overall HSt project. The Project includes the HSt tracks, structures, stations, traction power substations, maintenance facilities, and train vehicles. The HSt would use four different track types: at-grade, elevated by either a structure or on a retained fill platform, and below-grade tracks in a retained cut. The type of bridges that might be built includes full channel spans, large box culverts, or for some larger river crossings, piers within the ordinary high-water channel. This amendment provides for ecological restoration and enhancement work at approved mitigation sites.

Contact Information
Cliff Harvey
Water Resources Control Board, DWQ
1001 I Street., 15th Floor
Sacramento, CA 95814

916-558-1709

Location

Cities
Wasco Hanford Fresno Bakersfield
Counties
Kings
Zip
various
Total Acres
~114
Parcel #
various
State Highways
Hwy 43, others
Railways
UPRR, BNSF, SJVRR
Airports
Several Local Airports
Schools
Multiple
Waterways
Kings, Tule, & Kern Rivers; Cross & Poso Creeks
Township
variou
Range
variou
Section
variou
Base
various

Notice of Determination

Approving Agency
CA Public Utilities Commission
Approving Agency Role
Responsible Agency
Final EIR Available Location
N/A

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A Statement of Overriding Considerations was adopted for this project
N/A
(5) Findings were made pursuant to the provisions of CEQA
N/A