Caltrans D6 Issuance of Encroachment Permit: Lakeland Canal PG&E Relocations

122 Documents in Project

Summary

SCH Number
2009091126
Lead Agency
California High Speed Rail Authority
Document Title
Caltrans D6 Issuance of Encroachment Permit: Lakeland Canal PG&E Relocations
Document Type
NOD - Notice of Determination
Received
Posted
4/12/2023
Document Description
Site 1: Caltrans Postmile SR-43 TUL 13.613 Jack and bore under SR -43 approximately 100 linear feet from East to West. The bore pits will be placed outside Caltrans’ ROW. All soil within CT ROW will be reused at the site. All trenching will follow CAL-OSHA standards. Requesting shoulder closure on the East Side of SR-43. Site 2: Caltrans Postmile SR-43 TUL 13.620 Lane closures will be required for safe removal of overhead conductors for the entire width of SR-43 (approximately 10 min). Utility poles will not be stored within Caltrans Right-of-Way. Site 3: Caltrans Postmile SR-43 TUL 13.626 Trench on the East side of SR-43 along the shoulder for approximately 70 linear feet parallel to Caltrans ROW. Requesting shoulder closure on the East side of SR-43. Install two power poles outside of Caltrans ROW. All utility poles removed will not be stored within Caltrans Right-of-Way and will be hauled away.

Contact Information

Name
John Thomas
Agency Name
California Department of Transportation
Job Title
Senior Environmental Planner
Contact Types
Responsible Agency

Location

Cities
Corcoran
Counties
Kings, Tulare
Regions
Northern California
Cross Streets
Ave 96 at State Route 43
State Highways
State Route 43
Other Location Info
State Route 43 Post Mile 13.613-13.626

Notice of Determination

Approving Agency
California Department of Transportation
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.