Feasibility Study/Remedial Action Plan Lennar Mare Island Investigation Area B.1, Crane Test Area
2 Documents in Project
Summary
SCH Number
2009082058
Lead Agency
California Department of Toxic Substances Control
(DTSC)
Document Title
Feasibility Study/Remedial Action Plan Lennar Mare Island Investigation Area B.1, Crane Test Area
Document Type
NOD - Notice of Determination
Received
Posted
4/15/2010
Document Description
Preparation and DTSC approval of the Investigation Area B.1 Feasibility Study/Remedial Action Plan (FS/RAP) is pursuant to the requirements of the Comprehensive Environmental Response, Compensation and Liability Act of 1980, as amended by the Superfund Amendments and Reauthorization Act of 1986; the National Oil and Hazardous Substances Pollution Contingency Plan in Title 40 of the Code of Federal Regulations Part 300; and Chapter 6.8, Division 20, California Health & Safety Code. The FS/RAP proposes a remedial alternative for a portion of the former Mare Island Naval Shipyard, Vallejo, California containing total petroleum hydrocarbons as gasoline, motor oil and diesel, vinyl chloride, trichloroethene, 1,1,2,2-tetrachloroethane, arsenic lead, and benzo(a)pyrene. The remediation area is approximately 90-acres and is located in the north-central portion of the former Mare Island Naval Shipyard. IA B. is part of a larger parcel of land transferred from the United States Department of the Navy (navy) to Lennar Mare Island (LMI). LLC. Known as the Eastern Early Transfer Parcel (EETP). The FS/RAP is incorporated by reference.
Contact Information
Name
Janet Naito
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency
Phone
Location
Cities
Vallejo
Counties
Solano
Cross Streets
Mare Island
Zip
94592
Total Acres
5.4
State Highways
37,80
Schools
Mare Island ES
Waterways
San Pablo Bay
Notice of Determination
Approving Agency
Department of Toxic Substances Control
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.