The District is proposing to construct a new 500,000 gallon water storage tank on the North Shore of Lake Tahoe. The proposed 500,000 gallon water tank will replace an existing undersized 120,000 gallon water tank. The proposed tank will increase the storage capacity to provide adequate fire protection water and adequate storage for domestice consumption. This tank also serves as the reservoir for booster pumps which transport the water from this tank to the highest service area within the District. the planned tank dimensions are 36 ft high by 52 ft in diameter. After the proposed tank is online the existing 120,000 gallon tank will be demolished and the existing soft coverage will be revegetated. The existing and proposed sites are accessed from an existing Placer County dirt road/USFS off-highway-vehicle access road.

Contact Information

Name
Coral R. Taylor
Agency Name
North Tahoe Public Utility District
Contact Types
Lead/Public Agency

Location

Counties
Placer
Cross Streets
Lake Vista Rd, Commonwealth Dr
Zip
96143
Total Acres
0.72
Parcel #
110-060-010
State Highways
267
Schools
Kings Beach ES
Waterways
Griff Creek
Township
16N
Range
17E
Base
MDB&M
Other Location Info
City/Nearest Community: Kings Beach

Notice of Determination

Approving Agency
North Tahoe Public Utility District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print