Anaheim Regional Transportation Intermodal Center (ARTIC)

7 Documents in Project

Summary

SCH Number
2009071071
Lead Agency
Anaheim, City of (City of Anaheim)
Document Title
Anaheim Regional Transportation Intermodal Center (ARTIC)
Document Type
NOD - Notice of Determination
Received

Document Description
The total project site is ~19 acres, comprised of 16 acres for the facilities, two acres of OCTA and City roads and ROW, and less than one acre of Caltrans ROW. Approximately 18 of the 19 total acres are owned by OTCA and the City. The 405 parking spaces at the existing Anaheim Metrolink/Amtrak Station are not a part of the project construction site as no improvements are anticipated but will continue to be utilized as parking for the project. ARTIC is envisioned to include the development of an Intermodal Terminal, Public Plaza/Drop Off Area, the Stadium Pavilion, the Tracks/Platforms, Douglas Road Improvements, Katella Avenue improvements, and Surface Parking/Access. In addition to the surface access points, improvements envisioned for ARTIC include a pedestrian bridge to be constructed over Katella Avenue connecting the project site and the Honda Center, and a trail easement, adjacent to the Santa Ana River Trail along the east side of ARTIC between the railroad ROW and Katella Avenue. The ARTIC Intermodal Terminal is envisioned to include space ip to 310,000 sf. Platforms up to 86,000 sf, and a Stadium Pavilion up to 12,000 sf.

Contact Information
Jamie Lai
City of Anaheim
200 South Anaheim Boulevard, 2nd floor
Anaheim, CA 92805

(714) 765-5049

Location

Coordinates
33°48'14.8"N 117°52'38"W
Cities
Anaheim
Counties
Orange
Cross Streets
Katella Avenue/Douglass Road
Zip
92805
Total Acres
~19
State Highways
SR-57, I-5, SR-22
Railways
LOSSAN
Waterways
Santa Ana River

Notice of Determination

Approving Agency
City of Anaheim
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
City of Anaheim Planning Dept 200 S. Anaheim Blvd, Suite 162 Anaheim, CA 92805

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
Yes
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search