North and South Bodega Harbour High Pressure Zones 8-inch Intertie
Document Type
NOD - Notice of Determination
Received
Posted
8/20/2009
Present Land Use
GP: Rural Residential, Resource & Rural Development, Land Extensive Agriculture
Document Description
The project involves construction within the Bodega Bay public water system of an interconnection between 2 independent water service pressure zones within the Bodega Bay community. Project components would include construction of approximately 2,300' of an 8" diameter water main, installation of valves and accomplishing four connections to existing water mains.

Contact Information

Name
Rod Huls
Agency Name
Bodega Bay Public Utility District
Contact Types
Lead/Public Agency

Location

Counties
Sonoma
Cross Streets
Hwy 1 and Harbour Wy
Zip
94923
Parcel #
100-170-021, public right of way
State Highways
1
Schools
Bodega Bay ES
Waterways
Bodega Harbor, Pacific Ocean, Chenney Gultch
Township
6N
Range
11W
Section
rancho
Base
MDB&M
Other Location Info
Community: Bodega Bay

Notice of Determination

Approving Agency
Bodega Bay Public Utility District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.