Addendum
3 Documents in Project
Summary
SCH Number
2009052042
Lead Agency
Dublin Unified School District
Document Title
Addendum
Document Type
NOD - Notice of Determination
Received
Posted
6/30/2014
Present Land Use
PLU: Elementary School
Single-Family Residential/Public/Semi-Public Facility
Document Description
The Addendum includes the following changes to the project description of the adopted Dublin Elementary School Kindergarten Complex and 4th /5th Grade Classroom and Future 3rd Grade Classroom Project Mitigated Negative Declaration/Initial Study (MND/IS):
- The 3rd grade classroom building complex will include 6 rather than 5 classrooms.
- The existing playground will be extended, converting about 0.5 acre of playfields to paved surface.
- The existing playfields will be renovated to include new grass, decomposed granite path and new irrigation system designed to reduce water consumption. The amount of grass will be reduced and the area of drought tolerant plants will be increased. Two Bio-retention basins will be constructed to treat stormwater runoff from the 3rd grade classroom building complex and the south parking lot.
- An outdoor classroom and garden will be established to support school programs on about 0.5 acre of the existing playfields.
- The existing south parking lot will be extended to provide an additional 28 parking spaces; and a bio-retention basin will be constructed to treat stormwater runoff from the parking lot.
Contact Information
Name
Kim McNeely
Agency Name
Dublin Unified School District
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Dublin
Counties
Alameda
Cross Streets
Shannon Ave
Total Acres
15.68
Parcel #
941-169-31-2
State Highways
I-680
Schools
Murray ES
Notice of Determination
Approving Agency
Dublin Unified School District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.