Interstate 80 (I-80)/West El Camino Interchange Project (S15084800)

2 Documents in Project

Summary

SCH Number
2009052024
Lead Agency
City of Sacramento
Document Title
Interstate 80 (I-80)/West El Camino Interchange Project (S15084800)
Document Type
NOD - Notice of Determination
Received
Posted
8/12/2009
Document Description
The project consists of signalizing the eastbound and westbound off-ramp intersections with West El Camino. The signalization includes installing traffic interconnects and signal detector loops. Additional components of the project include widening the eastbound I-80 off ramp and portions of West El Camino between El Centro and the westbound on-rampo; constructing the necessary streetscape and/or utility improvements; constructing a 5 ft wide sidewalk along the east side of West El Camino Avenue between Orchard Land and El Centro Road; and constructing a 2 ft wide raised concrete median separating the eastbound and westbound lanes of West El Camino Avenue in front of the 49 er Truck Stop from the West El Camino Avenue/El Centro Road intersection to about 200 ft to the east. Where the existing pavement is structurally sound, the existing travel lanes and shoulders would be given an asphalt concrete overlay within the limits of the project. Where the existing pavement has visible structural deficiencies of has insufficient structural thickness, the asphalt concrete of the entire structural section will be replaced. The existing pavement striping would be modified to accommodate the new roadway configuration and would include Class II bicycle lanes along West El Camino Avenue.

Contact Information

Name
Scott Johnson
Agency Name
City of Sacramento
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Cross Streets
I-80 and West El Camino (I-80 Post Mile 1.3)
Zip
95833
Total Acres
22.7 +/-
State Highways
I-80, I-5
Schools
Two Rivers, Leroy Greene
Waterways
Sacramento River
Township
9N
Range
4E
Section
22
Base
MDB&M

Notice of Determination

Approving Agency
Sacramento City
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print