State Route 99/Elverta Road Interchange Project (California Endangered Species Act Inciddental Take Permit No. 2081-2012-002 (ITP))

5 Documents in Project

Summary

SCH Number
2009052019
Lead Agency
Sacramento County
Document Title
State Route 99/Elverta Road Interchange Project (California Endangered Species Act Inciddental Take Permit No. 2081-2012-002 (ITP))
Document Type
NOD - Notice of Determination
Received
Posted
11/6/2012
Present Land Use
roadway / agriculture
Document Description
The DFG issued the existing CESA ITP in order to address and authorize, as fully mitigated, the incidental take of giant garter snake (Thamnophis gigas), a species designated as Threatened under CESA. Minor Amendment No. 1, as approved, modifies the existing previously issued CESA ITP, modifying the 2012 work window by allowing work to continue until December 10th, 2012, and requiring the installation of snake fencing. In approving Minor Amendment No. 1, the DFG determined that, among other things, no substantial increase in the nature, or scope of the previous authorization provided by the CESA ITP, and that no new significant or substantially more severe environmental impacts than previously considered and disclosed would occur.

Contact Information

Name
Amy Kennedy
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Cross Streets
Elverta and SR 99
Zip
95836
Total Acres
109
State Highways
99
Waterways
E Drainage Canal
Township
10N
Range
4E
Base
MDB&M
Other Location Info
Nearest Community: Natomas

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project