Fall Creek Water Improvements Project

2 Documents in Project

Summary

SCH Number
2009042036
Lead Agency
City of Yreka
Document Title
Fall Creek Water Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
5/11/2009
Document Description
The Fall Creek Water Project improvements consist of the following 4 components: 1) construction of a new water storage tank to be located on Butcher Hill, 2) construction of a new filter pump station near Shelly Lane, 3) improvements to the backwash water recycling center and 4) replacement of water mains within teh City of Yreka. The objective of the proposed improvements to the City's existing water supply treatment and distribution system, is to provide reliable, safe domestic water during times of emergency, including power outages, backwash periods and periodic plant shutdowns due to high turbidity and pollen spikes. The project is designed to meet current fire flow needs within the City as well as existing and planned growth within the City.

Contact Information

Name
Pam Hayden
Agency Name
City of Yreka
Contact Types
Lead/Public Agency

Location

Cities
Yreka
Counties
Siskiyou
Cross Streets
Knapp and W. Lennox St, west of Sherman Blvd., east of Barham St, City of Yreka
Zip
96097
Parcel #
053-651-130, 140; 013-251-640
State Highways
I-5, SR 3
Railways
Yreka WEstern RR
Airports
No
Waterways
Yreka Creek, Humbug Creek, Greenhorn Creek
Township
45N
Range
7W
Section
22,23,
Other Information
Sections: 24, 3, 10

Notice of Determination

Approving Agency
City of Yreka
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print