49.6 MW Reciprocating Engine Generation Project

3 Documents in Project

Summary

SCH Number
2009032045
Lead Agency
Modesto Irrigation District
Document Title
49.6 MW Reciprocating Engine Generation Project
Document Type
NOD - Notice of Determination
Received
Posted
5/5/2009
Present Land Use
Light Industrial, Heavy Industrial, RPD
Document Description
The Modesto Irrigation District (MID) proposes to build a 49.6 MW Reciprocating Engine Power Plant adjacent to the existing Woodland Generation Station to be known as the "Woodland 3 Project" or the "Project." The Project will be comprised of 6 Wartsila reciprocating engines to be operated in simple-cycle mode, with no steam generation, but using selective catalytic reduction (SCR) and oxidation catalyst to reduce air emissions. The Project will also require the reconductoring of 2 existing MID 69-kilovolt (kV) subtransmission lines that tie into the existing PG&E natural gas supply pipeline. The Project would be located in the City of Modesto on a plot of land that has become available because the City is in the process of relocating and realigning Graphics Drive consistent with the vision set forth in the Redevleopment Agency's Master Plan as approved in September 2007.

Contact Information

Name
Richard Smith
Agency Name
Modesto Irrigation District
Contact Types
Lead/Public Agency

Location

Cities
Modesto
Counties
Stanislaus
Cross Streets
Woodland Ave and Graphics Dr
Zip
95351
Total Acres
10.2
Parcel #
029-013-001, 045, 046; 029-010-083
State Highways
SR 99, 132, 108
Railways
UPRR; Modesto & Empire Traction
Airports
No
Schools
ES, HS, Jr HS, College
Waterways
Dry Creek, Tuolumne River
Township
3S
Range
9E
Section
19,30
Base
MDB&M

Notice of Determination

Approving Agency
Modesto Irrigation District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.