Lost Horse Reservoir and Pipeline Project
5 Documents in Project
Summary
SCH Number
2009021073
Lead Agency
Indio Water Authority
Document Title
Lost Horse Reservoir and Pipeline Project
Document Type
NOD - Notice of Determination
Received
Posted
1/18/2011
Present Land Use
Z: W-1, Watercourse, Water Conservation
GP: Open Space/Recreation
Document Description
NOTE: Shortened Review/ Resubmittal
IWA proposes to construct a steel water reservoir, with a five mg capacity, in the Indio Hills located just north of the City boundaries. The proposed reservoir would be 180 feet in diameter and 40 feet in height. It would be supported by a floor plate and surround by a 20-foot wide process-stone road. An 8-foot high ornamental/security fence would surround the entire pad and a 20-foot wide, 900 foot long service road would be constructed to connect the reservoir site to an existing dirt road that provides access to the site. A 24-inch-diameter inlet transmission pipeline and 18-inch diameter water outlet transmission pipeline constructed of cement mortar and lined steel pipe would connect the reservoir to an existing pump station located near the Golf Club area at the Terra Lago Golf Course.
Contact Information
Name
Anders Wistrom
Agency Name
Indio Water Authority
Contact Types
Lead/Public Agency
Address
Phone
Location
Coordinates
Cities
Indio
Counties
Riverside
Cross Streets
Dillon Road/Ave 44
Zip
92203
Total Acres
3.4
Parcel #
601150012-17 and 20
State Highways
I-10
Waterways
unnamed blue line stream approx 3700 feet to the east
Township
5
Range
8S
Section
8
Base
SBB&M
Notice of Determination
Approving Agency
Indio Water Authority/ City of Indio
Approving Agency Role
Lead Agency
Determinations
(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.